Admin Guide - Enable Internal Only Tasks

    Last Modified On: October 30, 2026

     

    The Internal Only Tasks feature in Inspire Planner allows you to designate project tasks as internal-only, limiting the information visible to Digital Experience users and External Portal collaborators.
     

    When Internal Only is set to TRUE for a project task, users accessing the project through the Digital Experience or External Portal can still see the task details, but the task subject is displayed as “Internal Only Task”. The task’s chatter, file attachment indicator, and checklist items are also disabled.
     

    If preferred, Project Managers can populate an External Task Subject to display a customer-friendly task name to Digital Experience users and External Portal collaborators instead of the default “Internal Only Task” label.

     

    Please note:

    This help article has been updated to include features and enhancements available with the Inspire Planner November 2026 Major Release, which will be available in Production environments on November 24, 2026.

     

    Required Permissions

    You must be a Salesforce System Administrator to complete the steps in this article as it requires access to Salesforce Setup and Administration.

     

    Grant Access to Project Task Fields

    There are two (2) fields in the project task object that are used by this feature - "Internal Only" and "External Task Subject". Access to these fields is already included in the following Inspire Planner Permission Sets:

    • Inspire Planner Standard User - v1.12 Permission Set
    • Inspire Planner Standard User - Agile Management

     

    If you are using custom permission sets, you will need to edit them to grant access to these fields.

     

    1. Click on the Gear Icon in the top right corner and go to Setup.


       
    2. Enter "Permission Sets" in the Quick Find box and go to Permission Sets.


       
    3. Click on your custom permission set. The image below is just an example.


       
    4. Click on Object Settings.


       
    5. Go to Project Tasks.


       
    6. Click on Edit.


       
    7. Enable Read Access and Edit Access for both Internal Only and External Task Subject fields.


       
    8. Click on Save to save your changes. Repeat the steps above for all custom permission sets.

     

    Add Fields to Field Set

    You will need to add both "Internal Only" and "External Task Subject" to the Inspire Planner Custom Fields field set in the project task object so that they display as columns in the project Gantt.

     

    1. In Setup, go to Object Manager.


       
    2. Enter "Project Task" in the Quick Find box and go to Project Task.


       
    3. Go to Field Sets. Then, click on Inspire Planner Custom Fields. This is the field set that allows you to add fields as columns to the project Gantt.


       
    4. From the list of available fields on top, drag "Internal Only" and "External Task Subject" in the box labeled "In the Field Set". Then, click on Save.

     