Last Modified On: November 5, 2026
The Internal Only Tasks feature in Inspire Planner allows Project Managers to designate project tasks as internal-only, controlling the information visible to external users.
For External Portal collaborators, tasks marked as Internal Only are excluded from view altogether.
For Digital Experience users, the task remains visible, but its subject is displayed as “Internal Only Task” to protect internal information. The task’s Chatter, file attachment indicator, and checklist items are also disabled.
If preferred, Project Managers can populate the External Task Subject field to display a customer-friendly task name to Digital Experience users instead of the default “Internal Only Task” label.
Please note:
There are two (2) fields in the project task object that are used by this feature - "Internal Only" and "External Task Subject". You will find them in the list of columns available for you to display in the project Gantt.
Right-click on any column heading in the project Gantt and go to Columns. Then, scroll through the list of available fields and select the following:
You should now see them as columns in the project Gantt. You can drag and drop these columns to re-order and have them displayed according to your preference. For example, you can move them closer to the task subject, if preferred.
To set a project task as internal-only, simply set "Internal Only" to TRUE.
In the example below, the Digital Experience user sees the External Task subject instead of it being displayed as an internal-only task.
When External Portal collaborators print or export a Project, tasks marked as Internal Only are excluded from the printed or exported output altogether.
For Digital Experience users, Internal Only tasks remain included in printed and exported Projects, but the task subject is displayed as “Internal Only Task” unless an External Task Subject has been populated. This ensures that the information displayed in printed and exported versions is consistent with what users see on-screen.