FEB 2024 - Maintenance 1 - 1.353.3

    See below for what's included with Inspire Planner's Feb 2024 - Maintenance 1 - 1.353.3

     

    Released To: 
    All Environments: April 8, 2024 at 10 PM EST

     

    Available In: 
    All Environments: April 9, 2024

     

     

    Item #

     

    Resolved Issue

     

    Description

     

    Impact/Action Needed

           
    IP-451 Project - Delete Collaborator record when Project Team record is deleted When a project team record is deleted, the collaborator record for the project team member is now automatically deleted as well. No action required
           
    IP-519 Project - Status Report - Upload to File does not reference Custom Settings When a custom Status Report VF Page is configured in Custom Settings, it is now correctly referenced when the Status Report is generated and attached to Files. No action required
           
    IP-539 Project - Save As/Clone to inherit Project Time Zone For both Gantt VF and Gantt LWC projects - when users clone a Project using the "Save As" function, the new project now inherits the time zone of the source (original) project.  No action required
           
    IP-536 Project Sharing Job - Entity is deleted error 

    We've made adjustments to our logic to prevent errors when adjusting project collaborator records.

     No action required
           
    IP-523 Agile Projects - Adjust Version filter to only include Fix Version When filtering user stories (tasks) by Version in both the Kanban board and in the Backlog, it now only returns records based on Fix Version and no longer includes Affected Versions. No action required
           
    IP-527 Salesforce Task - Support Reassign Owner for Non-Licensed Users When users, who do not have an Inspire Planner License assigned, reassign SF Tasks by updating Owner field, the sysAssignedToIds of the related Project Task now correctly update. No action required
           
    IP-517 Time Tracker - Modal Window Failure in Service Console When accessing the Time Tracker component from Case object and pressing "New Entry" button in Daily View inside of service console, the modal window now correctly displays. No action required
           

     

     

    Gantt LWC 

    This section contains fixes we've made specific to the Gantt LWC. 

     

    Item #

     

    Resolved Issue

     

    Description

     

    Impact/Action Needed

           
    GLWC-158 Project - Chatter LWC component does not copy over links Links shared in the project and project task chatter are now correctly copied when cloning projects using Save As feature. No action required
           
    GLWC-203 Project - Print Format Issues We've made adjustments to the Print format in the Gantt LWC to match Gantt VF as close as possible.  No action required
           
    GLWC-221 Project - Display Icon in Priority Column The task Priority now displays as an icon instead of the picklist value. No action required
           
    GLWC-228 Project - Add option to hide Task Subject in Gantt Chart We've add a new icon that allows users to hide the task subject in the Gantt Chart. No action required
           
    GLWC-246 Project - Inheriting Global Default Project Settings between Gantt Versions If the template being used as the Global Default Project Setting is in Gantt VF, new projects created in Gantt LWC now correctly inherit the same settings from the Global Default ((i.e. Columns displayed, column order, column widths). No action required
           
    GLWC-247  Project - Applying project templates between Gantt Versions When a template that is in Gantt VF is applied during project creation to a project in Gantt LWC, the new project now correctly inherits the settings from the template (i.e. Columns displayed, column order, column widths, collapsed/expanded parent tasks). No action required
           
    GLWC-256 Project - Improve Saving Performance We've made adjustments to our Save logic in the Gantt LWC to improve performance. No action required
           
    GLWC-260 Project - Align Milestone Login with Gantt VF We've made adjustments to the logic that determines how Milestone Tasks plot in the Gantt LWC so that it is aligned with the logic in Gantt VF. No action required
           
    GLWC-264 Project - % Complete change indicator is incorrect Parent Task % Complete no longer displays a red change indicator when collapsing/expanding parent tasks. No action required
           
    GLWC-273 Project - Total Slack not calculating correctly Total Slack now calculates correctly for project tasks. No action required
           
    GLWC-282 Project - Increase max duration to 15 years The maximum duration supported in the Gantt LWC has been increased to 15 years. No action required
           
    GLWC-284 Project - Constraint Time not set correctly Constraint Time is now correctly being set for project tasks. No action required
           
    GLWC-286 Project - Percent and Multi-select Custom Fields Values entered in project task custom percent and multi-select fields now save and display correctly. No action required
           
    GLWC-288 Project - Timezone is not correctly converting from Template We've made adjustments to the Time Zone inheritance and Project time conversion logic so that Project Task Start Date/Time and Finish Date/Time are plotting correctly.

    Please see Project Timezone Assignment for more information.
     No action required
           
    GLWC-289 Project - Update Dependency Type to "Finish" instead of "End" We've updated the Dependency Type to use "Finish" instead of "End". No action required
           
    GLWC-296 Project - Allow for negative values in Currency fields In both Gantt VF and Gantt LWC - Currency Fields now support negative values. No action required
           
    GLWC-298 Project - Maintain user preferences when converting Gantt VF to Gantt LWC When a project is converted from Gantt VF to Gantt LWC, the user's viewing preferences are maintained (i.e. Columns displayed, column order, column widths, collapsed/expanded parent tasks). No action required
           
    GLWC-300 Project - All Icon Columns should be left of Subject When the Action Columns are displayed in the Gantt, they are now displayed to the left of the Task Subject. This includes the File Attachment Indicator, Porject Task Chatter Icon, Checklist Items, Open Project Task, and Salesforce Task Icon. No action required
           
    GLWC-303 Project - Actual Effort not rolling up on Parent Task In both Gantt VF and Gantt LWC - Actual Effort now correctly rolls up to Parent Tasks. No action required
           
    GLWC-305 Project - Actual Cost defaults to NULL In both Gantt VF and Gantt LWC - Actual Cost for Project Tasks now defaults to $0 instead of NULL. This allows for Remaining Budget to calculate when Budgeted Cost is populated. No action required
           
    GLWC-308 Project - Map to Legacy Start and Finish Date Fields Project Task Start and Finish Dates are now correctly being mapped to sysStartDateLegacy and sysFinishDateLegacy which are referenced by the Project Start and Finish Date fields. No action required
           
    GLWC-316 Project - Tasks that are "In Progress" are defaulting to 10% When converting a project from Gantt VF to Gantt LWC, tasks that have a status of "In Progress" (or equivalent custom status) now correctly retain the value in % Complete. No action required
           
           

    Tags

    Release Notes