Project and Project Task - % Complete

    The % Complete for both Project and Project Task is used to indicate progress, or how much of the task or project is done. 

     

    Project Task - How % Complete is Adjusted

    % Complete for Project Tasks is automatically updated when the status is adjusted. 


    Please Note:

    • The status values defined in the table below are the standard status picklist values that come as a default with Inspire Planner.
       
    • If you have custom status values defined in Custom Settings, then % Complete will adjust according to your custom status values. For example, if you have a custom status called "In Development" and have defined it as the equivalent of "In Progress" in custom settings, then when you adjust the task status to "In Development", % Complete will adjust according to how it would have adjusted for "In Progress". 
       
    • If the Project Task is assigned to multiple resources, then the Project Task % Complete is an aggregate of the related Salesforce Tasks % Complete.
       
    • Checklist Items, Time Entries (Actual Effort), Planned Effort, Budgeted Cost, and Actual Cost do not update % Complete.

     

    Task Status UpdatesTask % Complete will update to
    Not Started (default status)0%
    Not Started to In Progress10%
    From any status to Completed100%
    From any status to Deferred100%
    From Completed to In Progress90%
    From Completed to Waiting on someone else90%
    From any status except Completed to Waiting on someone elasewill not update value in % Complete
    From any status to Not Started0%

     

    Although % Complete defaults to the values defined in the table above when the task status is updated, % Complete can be and should be adjusted according to the progress made. This means that although % Complete defaults to 10% when you move a task from "Not Started" to "In Progress", it is recommended that you adjust the value for % Complete according to the progress you've made. If progress is now at 40%, then manually update % Complete to 40%.

     

    If the task status is "Completed" or "Deferred" (or any equivalent custom status) and you adjust % Complete from 100% to a lesser value greater than 0, it will then update the task status to "In Progress". If you update % Complete to 0%, then it will update the task status to "Not Started".

     

    When the related Salesforce Task % Complete is adjusted, this then adjusts the Project Task % Complete to the same value. However, if the Project Task is assigned to multiple resources, then the Project Task % Complete is an aggregate of the related Salesforce Tasks and is calculated as follows:

     

    Sum of related Saleforce Task % Complete / Number of related Salesforce Tasks

     

    This means that if:

     

    Resource 1 - Salesforce Task % Complete is 60%

    Resource 2 - Salesforce Task % Complete is 20%

     

    Then Project Task % Complete would be:

     

    (60% + 20%) / 2 

     

    Parent Tasks - How % Complete is Adjusted

    The Parent Task % Complete is an aggregate of the child tasks and will automatically update when either % Complete or Duration is adjusted for any of the child tasks. Since % Complete is an aggregate on the parent task, you cannot edit this value. You can only edit % Complete for the child tasks.

     

    The Parent Task % Complete is calculated as follows:

     

    (Task Duration / Total Duration for Group of Tasks) * % Complete

     

    If we look at the example below, the parent task % Complete is at 16%. This value is calculated from:

     

    (Task 1 Duration of 4 days / Total Task Group Duration of 10 days) * Task 1 % Complete of 40%

     

     

    As you continue to update either % Complete or Duration for any of the child tasks, the parent task % Complete will automatically recalculate. 

     

    If we look at the example below, the parent task % Complete is at 46%. This value is the sum of:

     

    (Task 1 Duration of 4 days / Total Task Group Duration of 10 days) * Task 1 % Complete of 100%

    (Task 2 Duration of 2 days / Total Task Group Duration of 10 days) * Task 2 % Complete of 30%

     

     

    Project - How % Complete is Adjusted

    The Project % Complete is a formula field and is calculated the same way that parent task % Complete is calculated. This means that you cannot manually edit the value for Project % Complete. 

     

    Unlike project tasks, adjusting the project status will not update project % Complete. 

     

    Please Note:

    There are two (2) workflow rules that are active by default in Inspire Planner that will automatically update the project status whenever the value in project % Complete updates.

     

    • Project - Enforce 100 When Completed - this automatically updates the project status to "Completed" when project % Complete is at 100%.
       
    • Set Project to In Progress - this automatically updates the project status to "In Progress" when project % Complete is > 0 and < 100%.

     

    This means that even if you manually update the project status to "Completed" but project % Complete is less than 100%, the next time a change is made to the project tasks where project % Complete is recalculated, if it is less than 100%, project status will update back to "In Progress".

     

    These workflow rules can be deactivated if you prefer to update project status values manually regardless of project % Complete. 

     

     

     

     


    Tags

    Project PlanProject Task List

    « Previous ArticleNext Article »