Last Modified On: October 28, 2024
Printing your Project is quick and easy. When you print a project, it exports the project first into either a PDF or a PNG file. You can then choose to print a physical copy if desired. This help article will show you how.
Please note:
Adjust the Gantt Chart so that it displays your desired time span. You can use the Left and Right arrows to move to the previous or next time span. Use the Zoom In and Zoom Out icons to zoom and out to a smaller or larger time span. If you would like to view the full timeline in the Gantt Chart, click on the Zoom to Full Timeline icon.
After you've adjusted the time span for the Gantt chart, click on the Print Project Plan icon located in the Project Toolbar.
A Print Settings dialogue will display where you can set your print preferences.
Once you've specified your print settings, click on Export. Inspire Planner will then export the project in the format you chose (PDF or PNG). You will be prompted to download the file and save it into a local folder.
It is possible to only print the task list or the Gantt Chart.
To print only the task list and not the Gantt Chart, simply close/hide the Gantt chart before clicking on the Print Project Plan icon. You can hide the Gantt chart by clicking on the Hide Gantt Chart icon. When the Gantt chart is hidden, then Inspire Planner ignores the Gantt Chart Range setting in the Print Settings dialogue.
To print only the Gantt chart and not the task list, simply close/hide the task list before clicking on the Print Project Plan icon. You can hide the task list by clicking on the Hide Task List icon in the project toolbar. When the task list is hidden, then Inspire Planner ignores the column setting in the Print Settings dialogue.
After hiding the task list, it is recommended that you adjust the Gantt chart using the Gantt chart icons. For example, if you intend to print the full project timeline or print the visible schedule, then use the zoom in/zoom out icons so that the Gantt chart displays the range and unit you want.
In the example below, if we want to see the project timeline in weeks, then we would use the zoom in icon to zoom into the timeline to display weeks. Do this before you click on the Print Project Plan icon.
If you don't want to display the task subject beside the task bars in the Gantt chart, you can choose to hide them by clicking on the Hide Task Subject icon in the Gantt Toolbar. This will hide the task subject in the Gantt chart and will also exclude it when printing projects. Do this before you click on the Print Project Plan icon.