Inspire Planner Formula Fields

    See below for a definition of all Formula Fields in Inspire Planner and how they are calculated.

     

    Project 

    Field NameDefinition / How It's Calculated
    % OverdueThe percentage the Project is overdue (Days Overdue / Project Duration)
    % CompleteTotal Project % Complete based on the % Complete of Project Tasks contained within the Project.
    % SlippageThe percentage the Project has slipped against the original baseline ((Actual Duration - Baseline Duration) / Baseline Duration)
    Actual DurationThe number of days the Project will take to complete based on actual Start and Finish Dates.
    Baseline DurationThe number of days the Project will take to complete based on baseline Start and Finish Dates
    Cost Performance Index (CPI)Measures the value of work completed against the Actual Cost. A CPI Value < 1 indicates costs where higher than budgeted while a CPI > 1 indicates that costs were less than budgeted (Earned Value / Actual Cost)
    Cost VarianceThe difference between Earned Value and Actual Cost. (Earned Value - Actual Cost)
    Cost Variance % The percentage of variance between Earned Value and Actual Cost ((Earned Value - Actual Cost) / Actual Cost)
    Days Overdue (Project)The number of days that the Project is overdue. If there is a Baseline Finish Date, it is calculated by taking the difference between the Actual Finish Date and the Baseline Finish Date. If there is no Baseline Finish Date, then it takes the difference between the current date and the Actual Finish Date.
    Days to CompletionThe number of days remaining until Project completion (Actual Finish Date - Today)
    DurationThe duration of the entire Project based on the Start and Finish Dates
    Earned EffortEffort earned based on % Complete of the Project (Total Planned Effort * % Complete)
    Earned ValueBudget earned to date based on the Project % Complete. (Budgeted Cost * % Complete)
    Effort VarianceThe difference between the Earned Effort and Actual Effort for the Project (Earned Effort - Total Actual Effort)
    Effort Variance %The percentage of variance between Earned Effort and Actual Effort ((Earned Effort - Total Actual Effort) / Total Actual Effort)
    Estimated at Completion (EAC)A forecast of how much the total project will cost. (Budgeted Cost / CPI)
    Finish VarianceThe difference between the baseline Finish date and the actual Finish Date (Actual Finish Date - Baseline Finish Date)
    Planned ValueDefined as the amount the Project should have earned based on current date against Project Duration and Budgeted Cost. If current date is less than Project Start Date, then Planned Value is at $0. (Project Duration - ((Project Finish Date - TODAY) + 1) / Project Duration) * Budgeted Cost)
    Owner NameDisplays the Project Owner Name
    Remaining BudgetThe difference between Budgeted Cost and Actual Cost (Budgeted Cost - Actual Cost)
    Remaining EffortThe difference between Planned Effort and Actual Effort (Total Planned Effort - Total Actual Effort)
    SlippageThe number of days the Project has slipped against the baseline. Negative value means that the Project completed ahead of schedule (Actual Duration - Baseline Duration)
    Start VarianceThe difference between baseline Start Date and actual Start Date (Start Date - Baseline Start Date)

     

     

    Project Task 

    Field NameDefinition / How It's Calculated
    % OverdueThe percentage the Project is overdue (Days Overdue / Project Duration)
    % CompleteTotal Project % Complete based on the % Complete of Project Tasks contained within the Project.
    % SlippageThe percentage the Project has slipped against the original baseline ((Actual Duration - Baseline Duration) / Baseline Duration)
    Actual DurationThe number of days the Project will take to complete based on actual Start and Finish Dates.
    Baseline DurationThe number of days the Project will take to complete based on baseline Start and Finish Dates
    Cost Performance Index (CPI)Measures the value of work completed against the Actual Cost. A CPI Value < 1 indicates costs where higher than budgeted while a CPI > 1 indicates that costs were less than budgeted (Earned Value / Actual Cost)
    Cost VarianceThe difference between Earned Value and Actual Cost. (Earned Value - Actual Cost)
    Cost Variance % The percentage of variance between Earned Value and Actual Cost ((Earned Value - Actual Cost) / Actual Cost)
    Days OverdueThe number of days that the Task is overdue. It takes the difference between the current date from the Task Actual Finish Date.
    Days to CompletionThe number of days remaining until Project completion (Actual Finish Date - Today)
    DurationThe duration of the Task based on the Start and Finish Dates
    Earned EffortEffort earned based on % Complete of the Project (Total Planned Effort * % Complete)
    Effort VarianceThe difference between the Earned Effort and Actual Effort for the Project (Earned Effort - Total Actual Effort)
    Effort Variance %The percentage of variance between Earned Effort and Actual Effort ((Earned Effort - Total Actual Effort) / Total Actual Effort)
    Estimated at Completion (EAC)A forecast of how much the total project will cost. (Budgeted Cost / CPI)
    Finish Date OnlyTask Finish Date 
    Finish VarianceThe difference between the baseline Finish date and the actual Finish Date (Actual Finish Date - Baseline Finish Date)
    Owner NameDisplays the Project Owner Name
    Remaining BudgetThe difference between Project Task Budgeted Cost and Actual Cost (Budgeted Cost - Actual Cost)
    Remaining EffortThe difference between Planned Effort and Actual Effort (Total Planned Effort - Total Actual Effort)
    Start Date OnlyTask Start Date
    Start VarianceThe difference between baseline Start Date and actual Start Date (Start Date - Baseline Start Date)
    SlippageThe number of days the Project has slipped against the baseline. Negative value means that the Project completed ahead of schedule (Actual Duration - Baseline Duration)
    Task Earned ValueBudget earned to date based on the Project Task % Complete. (Budgeted Cost * % Complete)
    Task Planned ValueDefined as the amount the Task should have earned based on current date against Task Duration and Budgeted Cost. If current date is less than Task Start Date, then Planned Value is at $0. (Task Duration - ((Task Finish Date - TODAY) + 1) / Task Duration) * Budgeted Cost)

     


    Tags

    Administration

    « Previous ArticleNext Article »